Hoover Dam Construction (1931-1936)
1931-1936
- Construction
- Contractors started April 20, 1931; all features complete by March 1, 1936
- Location
- Black Canyon on the Colorado River, about 30 miles southeast of Las Vegas
- Height
- 726.4 feet from foundation rock to the roadway on the crest
- Concrete
- 3.25 million cubic yards in the dam; 4.36 million including the powerplant and other works
- Concrete pours
- First concrete June 6, 1933; last May 29, 1935
- Workforce
- 21,000 men in total; average of 3,500 a day, peak of 5,218 in June 1934
- Payroll
- Average of $500,000 a month; wages ran from 50 cents to $1.25 an hour
- Contractor
- Six Companies, Inc., with a bid of $48,890,995.50
- Official fatalities
- 96 industrial deaths at the dam site; no one is buried in the concrete
- Where to see it today
- Hoover Dam Visitor Center, Power Plant Tour and Dam Tour (Bureau of Reclamation)
About
The Bureau of Reclamation wanted a dam that could tame the lower Colorado River and store a year-round water supply for the Southwest. Congress passed the Boulder Canyon Project Act in 1928, and in 1931 Interior Secretary Ray Lyman Wilbur chose Black Canyon, about 30 miles southeast of Las Vegas. The labour contract went to Six Companies of San Francisco, a group of six major Western builders, for $48,890,995.50, the largest labour contract the federal government had let up to that time.
The work was brutal. Temperatures in the canyon reached 110 to 120 degrees, and higher inside the diversion tunnels. The government rushed Boulder City into existence seven miles from the site to house workers, and crews drove four tunnels to divert the river before excavating the riverbed. The dam was poured as about 215 interlocking blocks, cooled by more than 582 miles of embedded pipe carrying ice water. Concrete placement ran from June 6, 1933, to May 29, 1935, and every feature was finished by March 1, 1936.
A total of 21,000 men worked on the dam, with a daily peak of 5,218 in June 1934. The Bureau of Reclamation counts 96 official "industrial fatalities": men killed at the site by drowning, blasting, falling rock, falls and equipment. Higher figures, such as 112, include deaths before construction began or from causes such as heat and illness. Reclamation is clear that no one is buried in the concrete.
For Las Vegas, the dam changed everything. The town had about 5,200 residents in 1930; the Online Nevada Encyclopedia puts the population at 7,500 by 1931. Dam workers spent their pay in town, especially after Nevada legalized casino gambling that March, and the construction site became a tourist attraction: 100,000 people visited in 1932 and 265,000 in 1934, many stopping in Las Vegas on the way. The dam began generating power in 1937, and Lake Mead's water supply later made the metro area's growth possible.
What to expect
Hoover Dam is open to the public daily from 5 a.m. to 9 p.m., and the Bureau of Reclamation's visitor services run daily from 9 a.m. to 5 p.m. except Thanksgiving and Christmas Day. Options include a Power Plant Tour, a self-guided exhibit tour and a guided Dam Tour through the inspection tunnels. Dam Tour tickets are sold on site only, first come, first served. As of August 19, 2026, Reclamation posted that Dam Tours were unavailable until further notice because of elevator repairs, while the other tours ran normally. Parking on the Nevada side costs $10 per vehicle.
More from the 1930s
Before and after
Good to know
- All vehicles pass through a security checkpoint on the Nevada side, and drivers may be asked to open the trunk, hood and storage areas.
- Interagency Passes such as America the Beautiful are not accepted for the Visitor Center or tours, because Hoover Dam is self-funded.
- The dam was renamed Boulder Dam in 1933 and Congress restored the name Hoover Dam in 1947.
- When finished in 1935 it was the tallest dam in the world, and from about 1938 to 1948 its powerplant was the largest hydroelectric plant in the world, according to Reclamation.
- Drones, firearms, explosives, fireworks and marijuana are all prohibited on Hoover Dam property under federal regulations.
- Visitors under 16 cannot take a tour by themselves, and tours include elevators and tunnels.
Questions about Hoover Dam Construction (1931-1936)
How long did it take to build Hoover Dam?
About five years. The contractors were allowed seven years from April 20, 1931, but concrete placement in the dam finished on May 29, 1935, and all features, including the powerplant, were complete by March 1, 1936, according to the Bureau of Reclamation. The crest height was reached about two years ahead of schedule.
How many people worked on Hoover Dam?
The Bureau of Reclamation says 21,000 men worked on the dam in total. The daily average was about 3,500, and the peak was 5,218 workers in June 1934. The average monthly payroll was $500,000, and hourly wages ranged from 50 cents to $1.25, averaging about 62.5 cents.
How many people died building Hoover Dam?
The official count is 96 industrial fatalities: men who died at the dam site from causes such as drowning, blasting, falling rock and falls. Larger figures, including 112, add deaths before construction began or from heat and illness. The Bureau of Reclamation states plainly that nobody is buried in the dam's concrete.
How did Hoover Dam affect Las Vegas?
It brought jobs, payrolls and tourists during the Depression. The Online Nevada Encyclopedia reports that Las Vegas grew from about 5,200 residents in 1930 to 7,500 by 1931, and that 265,000 people visited the dam site in 1934, many stopping in Las Vegas. The dam later supplied the water and power that let the valley grow.
Can you tour Hoover Dam?
Yes. The Bureau of Reclamation offers a Power Plant Tour, a self-guided exhibit tour and a guided Dam Tour, with the visitor center open 9 a.m. to 5 p.m. daily except Thanksgiving and Christmas. In August 2026 it announced that Dam Tours were paused for elevator repairs. Check usbr.gov for the current status before you drive out.
How tall is Hoover Dam?
Hoover Dam is 726.4 feet from foundation rock to the roadway on its crest, and the towers and ornaments on the parapet rise another 40 feet. It weighs more than 6.6 million tons and contains 3.25 million cubic yards of concrete, according to the Bureau of Reclamation's frequently asked questions.